15 weeks
£3.5m
Logistics & Distribution
Birmingham
JJL were asked to work with Kuehne + Nagel to consolidate an existing warehouse to facilitate a new contract for the fulfilment of Amazon orders.
The project involved:
“A very short timeline added complexity to this project which included the removal of existing and installation of new racking, an automated conveyor system, packing benches and floor grinding to facilitate the use of VNA FLTs.
From the very outset of the project JJL were engaged to co-ordinate the design and delivery of the solution. Thanks to great communication, flexibility and the can-do attitude of the JJL team; the tight deadline was achieved.”