Warehouse & Fulfilment Facility for major online retailer

Build Time

15 weeks

Budget

£3.5m

Sectors

Logistics & Distribution

Location

Birmingham

JJL were asked to work with Kuehne + Nagel to consolidate an existing warehouse to facilitate a new contract for the fulfilment of Amazon orders.

The project involved:

  • creation of a new staff entrance including security checkpoint and locker room
  • installation of a mezzanine floor for a canteen with personnel and goods lifts
  •  installation of new racking and sprinkler system
  • associated M&E works
  • external works
  • installation of automated conveyor system and pack benches
  • diamond grinding of existing floor to facilitate VNA FLTs

Gallery

Testimonial

“A very short timeline added complexity to this project which included the removal of existing and installation of new racking, an automated conveyor system, packing benches and floor grinding to facilitate the use of VNA FLTs.
From the very outset of the project JJL were engaged to co-ordinate the design and delivery of the solution. Thanks to great communication, flexibility and the can-do attitude of the JJL team; the tight deadline was achieved.”

- Adam Waldron, Senior Property Projects Manager