Southern Region Waitrose Frozen Food Distribution Centre

Build Time

26 weeks

Budget

£4.6m

Sectors

Logistics & Distribution

Location

Reading

Conversion of existing warehouse into a freezer store for the Waitrose contract for K+N Ltd.

The project involved removal of existing floor slab to lay freezer specification floor slab, erection of insulated envelope, energy efficient ammonia refrigeration system, Glycol heater mats, new HV supply to warehouse, new dock doors, high level racking, M&E works, fire alarm aspiration system and CCTV system, associated external works.

Gallery

Testimonial

“JJL Design and Build have completed numerous large and complex builds to an excellent standard for ourselves over the years. They were appointed as the Principal Contractor to deliver a replacement Southern Frozen DC as part of our Waitrose contract.
JJL are always extremely competitive in the tender phase and we find that their proactive management of all sub contractors, communication and problem solving abilities during the construction phase ultimately leads to a project that is completed on time, to budget and to an extremely high standard.”

- Lee Gough, General Manager Property Engineering

Send us an enquiry

Accreditations